Who's Online Now
0 members (), 20 guests, and 4 robots.
Key: Admin, Global Mod, Mod
September
S M T W T F S
1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30
Newest Members
Josephs, Javy89, Ropeguy67245, kywewa, Ingvar
10,040 Registered Users
Forum Statistics
Forums13
Topics7,385
Posts40,942
Members10,040
Most Online3,137
Apr 9th, 2026
Previous Thread
Next Thread
Print Thread
#9628 01/25/14 04:01 AM
Joined: Jan 2014
Posts: 1
F
Newbie
Newbie
F Offline
Joined: Jan 2014
Posts: 1
Hi,

I am new to the industry so please excuse me if my question is rather silly. I am an environmental engineer and currently doing an energy audit for an existing building. The building manager mentioned some day-to-day issues faced in the building and one of it is regarding the elevators.

There are 2 elevators on one end of the building, one serves 13 storeys and one serves 12 storeys. This is because there is a pool on the 13th storey on top of one of the elevators so it couldn't extend to that level. The building manager said that because of the different heights of the elevators they cannot be controlled using the same system. But people tend to press the call button on both elevators and take the fastest one to arrive, so energy is wasted on both elevators working when only one is needed.

I was wondering if this is really the case that the elevators cannot share a same control system? Or is there any particular control system that can solve this problem?

Thanks in advance! Looking forward to your replies smile

Joined: Jun 2013
Posts: 72
P
journeyman
journeyman
P Offline
Joined: Jun 2013
Posts: 72
Bullshit

They both can be controlled with the same group using swing car function

Joined: Dec 2010
Posts: 639
Likes: 4
E
addict
addict
E Offline
Joined: Dec 2010
Posts: 639
Likes: 4
There are and have been for a while now systems that can dispatch group elevators to the "uneven/odd floors" of any building such as you describe. Actually, with the micro processor based systems of the last 30 years, it's been possible. Any of the major companies can engineer software today to meet your buildings needs exactly. There are also secondary or after market manufacturers who can provide a quality product for any building design. Motion Control Engineering (mceinc.com), Computerized Elevator Control Corp. (swiftcec.com) are two companies worth mentioning.
Hope this helps.
*Now be sure to suggest to your "client" to upgrade their system even if the payback is 10 to 12 years in energy savings.
At least they'll have a system that will perform well for the next 30 years or more.

Joined: Sep 2012
Posts: 451
S
addict
addict
S Offline
Joined: Sep 2012
Posts: 451
I don't know what type of controls you have. I have couple different rises of 4 elevators, 2 out of the 4 cars only come up to the 10th floor and the other 2 service 2 floors above that. Not that big of a deal. They all run off the same group dispatcher.

Joined: Aug 2011
Posts: 563
U
addict
addict
U Offline
Joined: Aug 2011
Posts: 563
Originally Posted By: fiona_sg
Hi,

I am new to the industry so please excuse me if my question is rather silly. I am an environmental engineer and currently doing an energy audit for an existing building. The building manager mentioned some day-to-day issues faced in the building and one of it is regarding the elevators.

There are 2 elevators on one end of the building, one serves 13 storeys and one serves 12 storeys. This is because there is a pool on the 13th storey on top of one of the elevators so it couldn't extend to that level. The building manager said that because of the different heights of the elevators they cannot be controlled using the same system. But people tend to press the call button on both elevators and take the fastest one to arrive, so energy is wasted on both elevators working when only one is needed.

I was wondering if this is really the case that the elevators cannot share a same control system? Or is there any particular control system that can solve this problem?

Thanks in advance! Looking forward to your replies smile


With old relay logic or the newer electronic control anything can be achieved. What you describe is virtually the same as a basement level opening that is only served by 1 lift except your situation is at the top of the building. It appears to me as it was simply easier, or maybe they were lazy, to have 2 separate control systems for these 2 lifts. So the answer is of course you can and there is no reason why if your going to upgrade them that this cant happen.

Joined: Nov 2009
Posts: 146
mushroom
mushroom
Joined: Nov 2009
Posts: 146
Originally Posted By: uppo72
Originally Posted By: fiona_sg
Hi,

I am new to the industry so please excuse me if my question is rather silly. I am an environmental engineer and currently doing an energy audit for an existing building. The building manager mentioned some day-to-day issues faced in the building and one of it is regarding the elevators.

There are 2 elevators on one end of the building, one serves 13 storeys and one serves 12 storeys. This is because there is a pool on the 13th storey on top of one of the elevators so it couldn't extend to that level. The building manager said that because of the different heights of the elevators they cannot be controlled using the same system. But people tend to press the call button on both elevators and take the fastest one to arrive, so energy is wasted on both elevators working when only one is needed.

I was wondering if this is really the case that the elevators cannot share a same control system? Or is there any particular control system that can solve this problem?

Thanks in advance! Looking forward to your replies smile


With old relay logic or the newer electronic control anything can be achieved. What you describe is virtually the same as a basement level opening that is only served by 1 lift except your situation is at the top of the building. It appears to me as it was simply easier, or maybe they were lazy, to have 2 separate control systems for these 2 lifts. So the answer is of course you can and there is no reason why if your going to upgrade them that this cant happen.


I think lazy is the word....you could do this almost from the invention of the elevator so me thinks the company involved either is incompetent or just in it for a laugh!!


I used to be indecisive....now i"m not so sure
Joined: Apr 2014
Posts: 18
S
stranger
stranger
S Offline
Joined: Apr 2014
Posts: 18
It will require some engineering but a lot of options exist.
The easyest would be a plc(programmable logic controler). But relay logic or a microprocessor overlay could be used to make the elevators share the traffic load.


Link Copied to Clipboard
Photo Gallery
service tool laptop
service tool laptop
by dunkdadrunk, February 4
rip orona
rip orona
by epic_ecodisc, January 7
what controller is this?!
what controller is this?!
by Alex_ELMAN, December 4
HW PM
HW PM
by Chris, January 13
PECCO PH5000 Overspeed Governor
PECCO PH5000 Overspeed Governor
by stankap, September 24
Drive sheave
Drive sheave
by jkh, October 10
The best helper.
The best helper.
by Adrian, August 8
Powered by UBB.threads™ PHP Forum Software 8.0.0
(Release build 20240826)
Responsive Width:

PHP: 8.3.33 Page Time: 0.026s Queries: 28 (0.005s) Memory: 3.0322 MB (Peak: 3.5926 MB) Data Comp: Off Server Time: 2026-09-21 07:40:00 UTC
Valid HTML 5 and Valid CSS